Operation of west access road for freeway of Esfahan
Project specification
Project: Operation of west access road for freeway of Esfahan
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision : : Moshara and pasilo Consulting Engineers JV
End time: 18 Feb 2009
Start time: 16 Mar 2004
Specifications
Operation of the West Access Road of Esfahan Freeway from Km. 0+000 to Km. 94+770 in length of 770.94 Km. including substructure, pavement construction, technical buildings, special technical buildings including non-leveled bridge and hot mix asphalt according to drawings and specifications, preparing and installation guardrail installation, traffic painting and traffic signs in Phase 1 & 2 in 78 Km. and road tolls room section in Phase 1
1. Najafabad non-leveled intersection, two bridge in length of 66 and with the width of 12 m.
2. Gavpiseh non-leveled intersection, two bridge in length of 117 and with the width of 12 m.
Asphalt: 645,311Ton
Concrete Work:127,483 M3
Excavation: 2,219,228M3
Steel Work: 4,901,492kg
Earth Moving: 6,340,346M3
-
Finishing operations of west access road freeway of Esfahan
Project specification
Project: Finishing operations of west access road freeway of Esfahan
Project Owner: : Ministry of Roads & Urban Development
Consulting & Supervision : : Moshara and pasilo Consulting Engineers JV
End time:
Start time: 12 Aug 2012
Specifications
Operation west access road of Esfahan Freeway from Km. 75+000 to Km. 100+89 in length of 1.14 Km. including substructure, pavement construction, technical buildings, special technical buildings and hot mix asphalt according to drawings and specifications, preparing and installation guardrail installation, traffic painting and traffic signs in road tolls room
Asphalt: 106,553Ton
Concrete Work:80,929 M3
Excavation: 1,394,708M3
Steel Work: 6,167,824kg
Earth Moving: 1,333,385M3
-
Kashan-Esfahan Freeway, Part X
Project specification
Project: Kashan-Esfahan Freeway, Part X
Project Owner: Constriction and Maintenance Company
Consulting & Supervision : : Farashar Consulting Company
End time: 31 Aug 2004
Start time: 1 Mar 2003
Specifications
Finishing Kashan-Esfahan Freeway, Part X with the length of 12.5 Km. from Km. 213+500 to Km. 226+000 including foundation excavation, earth excavation, concrete and reinforced concrete for technical buildings, earth moving operation for freeway body; base and sub.-base layers, asphalt Layers, steel works and other
Asphalt: 160,541Ton
Concrete Work: 5,685M3
Excavation: 176,769M3
Steel Work: 122,628kg
Earth Moving: 210,673M3
-
Kashan-Esfahan Freeway, Part IX
Project specification:
Project: Kashan-Esfahan Freeway, Part IX
Project Owner: Constriction and Maintenance Company
Consulting & Supervision : taradodd rah Consulting Company
End time: 22 Jun 2004
Start time: 14 Apr 1999
Specifications:
Constructing and finishing substructure and pavement construction of Kashan-Esfahan Freeway Part IX in Km. 211.19 including earth filling, excavation, concrete pouring, cliff-cutting, asphalt and other for operations
Asphalt:234,582 Ton
Concrete Work:25,633 M3
Excavation:520,889M3
Steel Work: 397,545kg
Earth Moving:1.531.196 M3
-
Kashan-Natanz-Esfahan Freeway, Part VI
Project specification:
Project: Kashan-Natanz-Esfahan Freeway, Part VI
Project Owner: Constriction and Maintenance Company
Consulting & Supervision : : Farashar Consulting Company
End time: 20 Nov 2002
Start time: 21 May 1997
Specifications:
nishing Kashan-Esfahan Freeway, Part X with the length of 24 Km. from Km. 130 to Km. 154 including foundation excavation, earth excavation, concrete and reinforced concrete for technical buildings, earth moving operation for freeway body; base and sub.-base layers, asphalt Layers, steel works and other
Asphalt: 359,483Ton
Concrete Work: 79,364M3
Excavation: 1.153,048M3
Steel Work: 2,379.826kg
Earth Moving: 2,480,916M3
-
Kashan-Natanz-Esfahan Freeway, Part V
Project specification
Project: Kashan-Natanz-Esfahan Freeway, Part V
Project Owner: Constriction and Maintenance Company Consulting & Supervision : farashar consulting company
End time: 20 Nov 2002
Start time: 23 Jul 1997
Specifications
nishing Kashan-Esfahan Freeway, Part X with the length of 26 Km. from Km. 104 to Km. 130 including foundation excavation, earth excavation, concrete and reinforced concrete for technical buildings, earth moving operation for freeway body; base and sub.-base layers, asphalt Layers, steel works and other
Asphalt:398,839 Ton
Concrete Work: 98,542M3
Excavation: 1,246,200M3
Steel Work: 2,310,660kg
Earth Moving: 1,723,618M3