Rehabilitation and Retrofitting, Shiraz-Safashahr Highway
Project specification:
Project: Rehabilitation and Retrofitting, Shiraz-Safashahr Highway
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision : tadbir Consulting Company
End time: 21 Nov 2010
Start time: 11 Mar 2007
Specifications:
Retrofitting Shiraz-SafaShahr Highway with the length of 180 Km. from Shiraz to SafaShahr, return way from SafaShahr to Shiraz including excavation, dressing asphalt, patching, crack filing, asphalt leyars, technical buildings, and traffic sign.
Asphalt:894,356 Ton
Concrete Work:139 M3
Excavation:8,867M3
Steel Work:408 kg
Earth Moving:---
-
Rehabilitation and Retrofitting for Meimeh-Salafchegan Highway, Part I
Project specification
Project: Rehabilitation and Retrofitting for Meimeh-Salafchegan Highway, Part I
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision :iran oston Consulting Company
End time: 12 Jun 2001
Start time: 29 Dec 1996
Specifications
Hot Mix Asphalt, a section of Meimeh-Salafchegan in present road in length of 40.800 Km. of Km. 100+000
Asphalt: 192.853Ton
Concrete Work: ---
Excavation: ---
Steel Work: ---
Earth Moving: ---
-
(Rehabilitation and Retrofitting for Meimeh-Salafchegan Highway, Part II (A
Project specification:
Project: Rehabilitation and Retrofitting for Meimeh-Salafchegan Highway, Part II (A)
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision : Iran oston Consulting Company
End time: 16 Jul 2002
Start time: 8 Jan 1997
Specifications:
Hot Mix Asphalt Lining, a section of Meimeh-Salafchegan in present road in length of 50 Km. of Km. 50+000 to Km. 100+000
Asphalt: 177,487Ton
Concrete Work: ---
Excavation: 444
Steel Work: ---
Earth Moving: ---
-
(Rehabilitation and Retrofitting for Meimeh-Salafchegan Highway, Part II (B
Project specification
Project: Rehabilitation and Retrofitting for Meimeh-Salafchegan Highway, Part II (B)
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision : iran oston Consulting Company
End time: 2 Jul 2002
Start time: 8 Jan 1997
Specifications
Hot Mix Asphalt Lining, a section of Meimeh-Salafchegan in present road in 50 Km. of Km. 0+000 to Km. 50+000
Asphalt:209.116 Ton
Concrete Work: ---
Excavation: 888M3
Steel Work: ---
Earth Moving: ---
-
Rehabilitation and Retrofitting Meimeh-Alavijeh (East Band) T-way
Project specification:
Project: Rehabilitation and Retrofitting Meimeh-Alavijeh (East Band) T-way
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision : iran oston Consulting Company
End time: 7 Nov 2002
Start time: 10 Jan 1999
Specifications:
Hot mix asphalt lining of east band, Meimeh-Alavijeh Three-Way with length of 60 Km. traffic painting and widening the road in the present and operations relevant to 15 Km. of end of way
Asphalt: 167.504Ton
Concrete Work: 948M3
Excavation: 156.210M3
Steel Work:5.640 kg
Earth Moving: 117.171M3
-
(salafchegan-arak highway ( rahjerd variation
Project specification
Project: salafchegan-arak highway ( rahjerd variation)
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision :
End time: 5 Sep 2000
Start time: 7 Dec 1998
Specifications :
Variant construction of the road in Dehjerd between Km. 46+400 and Km. 55+360 in one band relevant to Arak-Salafchegan Main Road Part IV (2nd Band on the left side from Arak)
Asphalt: 61.600Ton
Concrete Work: 20.626M3
Excavation: 179.124M3
Steel Work:358.818 kg
Earth Moving: 649.052M3
-
Arak-Salafchegan Highway, Part III
Project specification
Project; Arak-Salafchegan Highway, Part III
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision :
End time: 12 Nov 2001
Start time: 25 Jul 1999
Specifications
Arak-Salafchegan 4-Band Highway, Part III between Km. 5+430 to Km. 27+500 with length of 22.1 Km. including substructure and pavement construction, technical buildings and hot mix asphalt lining according to drawings and specifications, guardrail installation, traffic painting and traffic signs for operation and finishing
Asphalt: 86,845 Ton
Concrete Work: 13,234M3
Excavation: 133,698M3
Steel Work:284,703 kg
Earth Moving: 246,877M3
-
Arak-Salafchegan Highway, Part III
Project specification
Project: Arak-Salafchegan Highway, Part III
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision
End time: 12 Nov 2001
Start time: 12 Sep 2000
Specifications:
Arak-Salafchegan 4-Band Highway, between Km. 5+430 to Km. 27+500 including substructure and pavement construction, technical buildings and hot mix asphalt lining according to drawings and specifications, guardrail installation, traffic painting and traffic signs for operation and finishing
Asphalt: 57,350Ton
Concrete Work: 391M3
Excavation: 30,341M3
Steel Work: ---
Earth Moving: 130,933M3
-
Neyzar Bridge constriction and, Meimeh-Salafchegan Highway, 2nd Band asphalt
Project specification
Neyzar Bridge constriction and, Meimeh-Salafchegan Highway, 2nd Band asphalt:Project
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision : iran oston consulting company
End time: 19 Jun 2000
Start time: 27 Jan 1997
Specifications
asphalt, a section of Part V, Part VI (A) & Part VI (B), Construction of Neyzar Bridge in the 2nd Band, Meimeh-Salafchegan Highway
Asphalt: 157,884Ton
Concrete Work: 5,526M3
Excavation: 34,727M3
Steel Work: ---
Earth Moving: 11,375M3
-
Meimeh-Delijan-Salafchegan Highway, 2nd Band, Part V
Project specification
Project: Meimeh-Delijan-Salafchegan Highway, 2nd Band, Part V
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision : iran oston consulting company
End time: 28 Sep 1999
Start time: 8 Mar 1997
Specifications
Construction of Part V, 2nd Band of Meimeh-Delijan-Salafchegan Highway from Km. 0+000 to Km. 19+000 Part III in 19 Km. including substructure and pavement (excluding asphalt) and technical buildings throughout the way
Asphalt: ---
Concrete Work: 23,705M3
Excavation: 76,952M3
Steel Work: ---
Earth Moving: 322,301M3
-
Meimeh-Salafchegan Highway, 2nd Band, Part IV & a section of Part V
Project specification
Project: Meimeh-Salafchegan Highway, 2nd Band, Part IV & a section of Part V
Project Owner: Ministry of Roads & Urban Development
Consulting & Supervision : iran oston consulting company
End time: 27 Sep 1999
Start time: 27 Jan 1997
Specifications
Highway construction and asphalt Part IV, 2nd Band of Meimeh-Delijan-Salafchegan Highway in length of 385.22 Km. (including Part I of Km. 0+000 to Km. 3+187, Part II of Km. 0+000 to Km. 19+1999) and a section of Part V in 16 Km. (from Km. 0+000 to Km. 16+000 Part III), in total 386.38 Km. including hot mix asphalt, traffic painting and traffic signs and guardrail installation
Asphalt: 186.090Ton
Concrete Work: ---
Excavation: ---
Steel Work: ---
Earth Moving: ---